Everyone who has ordered a 991 Please Read. (Collection of Info)
#198
Racer
User Name: Scottish Pete
Model: MY 2015 991 C2S
Date Ordered: 07/25/14
Vehicle Fixed: 09/05/14
Suggested Build Date: 10/03/14
Actual Build Date:
Completion:
On Vessel:
Arrived at Dealership: 12/12/14
Delivery to Customer:
My freeze date a week from tomorrow on September 5th is four weeks before the suggested build date on Friday, October 3rd. Do they build cars seven days a week?
Model: MY 2015 991 C2S
Date Ordered: 07/25/14
Vehicle Fixed: 09/05/14
Suggested Build Date: 10/03/14
Actual Build Date:
Completion:
On Vessel:
Arrived at Dealership: 12/12/14
Delivery to Customer:
My freeze date a week from tomorrow on September 5th is four weeks before the suggested build date on Friday, October 3rd. Do they build cars seven days a week?
Last edited by Scottish Pete; 08-27-2014 at 12:20 AM. Reason: Wrong build date at bottom sentence.
#199
Three Wheelin'
But here I go again . . . I spent time yesterday with my dealer and am near a final config. I worked with him on his config system and never saw an option for deviated stitching with the Dashboard Trim in Leather option. I've only seen "deviating" stitching with that option on two-tone interiors. Do you know the code and cost for it?
btw Jonathan - it's and incredible build. I know the time it takes to figure all of that out.
#200
User Name: drmatara
Model: MY 2015 991 Cab
Date Ordered: 04/28/14
Vehicle Fixed: 7/11/2014
Suggested Build Date: 08/01/14
Actual Build Date: 07/28/14
Completion: 07/29/14
On Vessel: 08/07/14. Due Panama Canal 8/23. Due Port of San Diego 9/3
Arrived at Dealership: MM/DD/YY
Delivery to Customer: MM/DD/YY
Model: MY 2015 991 Cab
Date Ordered: 04/28/14
Vehicle Fixed: 7/11/2014
Suggested Build Date: 08/01/14
Actual Build Date: 07/28/14
Completion: 07/29/14
On Vessel: 08/07/14. Due Panama Canal 8/23. Due Port of San Diego 9/3
Arrived at Dealership: MM/DD/YY
Delivery to Customer: MM/DD/YY
Model: MY 2015 991 Cab
Date Ordered: 04/28/14
Vehicle Fixed: 7/11/2014
Suggested Build Date: 08/01/14
Actual Build Date: 07/28/14
Completion: 07/29/14
On Vessel: 08/07/14. Port of San Diego 9/2
Arrived at Dealership: 09/10/14
Delivery to Customer: 09/11/14
Finally here, I'll go and pick it up tomorrow
Last edited by drmatara; 09-10-2014 at 11:39 PM.
#201
Rennlist Member
User Name: drmatara
Model: MY 2015 991 Cab
Date Ordered: 04/28/14
Vehicle Fixed: 7/11/2014
Suggested Build Date: 08/01/14
Actual Build Date: 07/28/14
Completion: 07/29/14
On Vessel: 08/07/14. Due Port of San Diego 9/2
Arrived at Dealership: 09/10/14
Delivery to Customer: 09/11/14
Finally here, I'll go and pick it up tomorrow
Model: MY 2015 991 Cab
Date Ordered: 04/28/14
Vehicle Fixed: 7/11/2014
Suggested Build Date: 08/01/14
Actual Build Date: 07/28/14
Completion: 07/29/14
On Vessel: 08/07/14. Due Port of San Diego 9/2
Arrived at Dealership: 09/10/14
Delivery to Customer: 09/11/14
Finally here, I'll go and pick it up tomorrow
#202
Rennlist Member
User Name: fjpdds
Model: 991 Targa 4S
Date Ordered: 04/16/14
Suggested Build Date: 07 2014
Actual Build Date: TBD
Completion:TBD
On Vessel: TBD
PDI at Port (Brunswick) 9/8/14 We are trucking now!
Delivery to Customer: 09/11/2014 (est)
I pick it up Thursday 9/11
Model: 991 Targa 4S
Date Ordered: 04/16/14
Suggested Build Date: 07 2014
Actual Build Date: TBD
Completion:TBD
On Vessel: TBD
PDI at Port (Brunswick) 9/8/14 We are trucking now!
Delivery to Customer: 09/11/2014 (est)
I pick it up Thursday 9/11
#203
#204
Congrats to you too...isn't it great that we get our 911s on 9/11?
#205
Rennlist Member
Congrats drmatara. Cheers on the 9/11 delivery! A few pics. Getting expel clear shield installed so delayed first drive until Saturday.
Last edited by fjpdds; 09-11-2014 at 11:00 PM. Reason: typo
#206
Racer
User Name: Scottish Pete
Model: MY 2015 991 C2S
Date Ordered: 07/25/14
Vehicle Fixed: 09/05/14
Suggested Build Date: 10/09/14
Actual Build Date:
Completion:
On Vessel:
Arrived at Dealership: 12/12/14
Delivery to Customer:
My order is in preproduction V210 (freeze point reached), the date it will enter the body shop has been pushed back from October 3rd to October 9th.
Model: MY 2015 991 C2S
Date Ordered: 07/25/14
Vehicle Fixed: 09/05/14
Suggested Build Date: 10/09/14
Actual Build Date:
Completion:
On Vessel:
Arrived at Dealership: 12/12/14
Delivery to Customer:
My order is in preproduction V210 (freeze point reached), the date it will enter the body shop has been pushed back from October 3rd to October 9th.
#207
Racer
User Name: Scottish Pete
Model: MY 2015 991 C2S
Date Ordered: 07/25/14
Vehicle Fixed: 09/05/14
Vehicle Entry To Body Shop Planned Date: 10/03/14
Vehicle Entry to Body Shop Actual: 9/29/14
Vehicle Exit Production Expected Date: 10/03/14
Vehicle Completion Expected Date: 10/03/14
Entry Port Emden: 10/10/14
Exit Port Emden: 10/24/14 (Auriga Leader)
Entry Port San Diego Expected: 11/21/14
Exit Port San Diego Expected: 12/05/14
Dealer Inventory Expected: 12/12/14
Delivery to Customer:
I stopped at the Fresno dealership today on a trip up to the airport and had them print out an update on my order. The previous report had my car moved from 10/03 start of production to 10/09 but got moved back and actually started production on 9/29. It will be on the Auriga Leader scheduled to leave Emden for San Diego on 10/24. The past few ships have made the trip to San Diego in 25-26 days so I could have my car by Thanksgiving . . . if it moves through the San Diego dock as quickly as the last shipment which were released in only three days.
So my car entered production two days ago . . . uh, do I have any concerns being assembled the first week of Oktoberfest?!!
Model: MY 2015 991 C2S
Date Ordered: 07/25/14
Vehicle Fixed: 09/05/14
Vehicle Entry To Body Shop Planned Date: 10/03/14
Vehicle Entry to Body Shop Actual: 9/29/14
Vehicle Exit Production Expected Date: 10/03/14
Vehicle Completion Expected Date: 10/03/14
Entry Port Emden: 10/10/14
Exit Port Emden: 10/24/14 (Auriga Leader)
Entry Port San Diego Expected: 11/21/14
Exit Port San Diego Expected: 12/05/14
Dealer Inventory Expected: 12/12/14
Delivery to Customer:
I stopped at the Fresno dealership today on a trip up to the airport and had them print out an update on my order. The previous report had my car moved from 10/03 start of production to 10/09 but got moved back and actually started production on 9/29. It will be on the Auriga Leader scheduled to leave Emden for San Diego on 10/24. The past few ships have made the trip to San Diego in 25-26 days so I could have my car by Thanksgiving . . . if it moves through the San Diego dock as quickly as the last shipment which were released in only three days.
So my car entered production two days ago . . . uh, do I have any concerns being assembled the first week of Oktoberfest?!!
#208
Rennlist Member
User Name: Intruder224
Model: MY 2015 991 Targa 4S
Date Ordered: 09/12/14
Vehicle Fixed: 09/30/14
Estimated Build Date: 10/17/14
Actual Build Date:
Estimated Completion: 10/24/14
On Vessel: 11/14/14
Est. Arrival at Port: 12/05/14
Arrived at Dealership: 12/17/14
Delivery to Customer:
My order is in preproduction V210 (freeze point reached). This was quite a surprise as my original freeze date was 30 Oct. I called the SA a few days ago and he said Porche had moved up the date. I'm getting excited!!!
Model: MY 2015 991 Targa 4S
Date Ordered: 09/12/14
Vehicle Fixed: 09/30/14
Estimated Build Date: 10/17/14
Actual Build Date:
Estimated Completion: 10/24/14
On Vessel: 11/14/14
Est. Arrival at Port: 12/05/14
Arrived at Dealership: 12/17/14
Delivery to Customer:
My order is in preproduction V210 (freeze point reached). This was quite a surprise as my original freeze date was 30 Oct. I called the SA a few days ago and he said Porche had moved up the date. I'm getting excited!!!
Last edited by intruder224; 10-06-2014 at 10:30 AM. Reason: updated info
#209
. . . I spent time yesterday with my dealer and am near a final config. I worked with him on his config system and never saw an option for deviated stitching with the Dashboard Trim in Leather option. I've only seen "deviating" stitching with that option on two-tone interiors. Do you know the code and cost for it?
https://rennlist.com/forums/991/7085...e-and-you.html
Hope you found the answer regardless and good luck!
Saludos,
Eduardo
Carmel
#210
Racer
User Name: Scottish Pete
Model: MY 2015 991 C2S
Date Ordered: 07/25/14
Vehicle Fixed: 09/18/14
Vehicle Entry to Body Shop Actual Date: 9/29/14
Vehicle Exit Production Actual Date: 10/06/14
Vehicle Completion Actual Date: 10/06/14
Entry Port Emden Actual Date: 10/07/14
Exit Port Emden Planned Date: 10/24/14
Exit Port Emden Expected Date: 10/17/14
Entry Port San Diego Planned Date: 11/28/14
Entry Port San Diego Expected Date: 11/21/14
Release for Transport - Monroney printed:
Exit Port San Diego Planned Date: 11/28/14
Dealer Inventory Planned Date: 12/12/14
Dealer Inventory Expected Date: 12/05/14
Delivery to Customer:
My Carrera S arrived at the dock at Emden on 10/07/14 only one day after completion and two days before the Hestia Leader sailed for San Diego. Not sure if it got loaded, the new printout from my dealer today is showing it leaving Emden on 10/17, however the next ship showing on the Volkswagen Logistics on the PWL website leaving for San Diego is on 10/24. Maybe they are getting too many cars backed up on the dock and are adding an additional ship to San Diego on 10/17?
Model: MY 2015 991 C2S
Date Ordered: 07/25/14
Vehicle Fixed: 09/18/14
Vehicle Entry to Body Shop Actual Date: 9/29/14
Vehicle Exit Production Actual Date: 10/06/14
Vehicle Completion Actual Date: 10/06/14
Entry Port Emden Actual Date: 10/07/14
Exit Port Emden Planned Date: 10/24/14
Exit Port Emden Expected Date: 10/17/14
Entry Port San Diego Planned Date: 11/28/14
Entry Port San Diego Expected Date: 11/21/14
Release for Transport - Monroney printed:
Exit Port San Diego Planned Date: 11/28/14
Dealer Inventory Planned Date: 12/12/14
Dealer Inventory Expected Date: 12/05/14
Delivery to Customer:
My Carrera S arrived at the dock at Emden on 10/07/14 only one day after completion and two days before the Hestia Leader sailed for San Diego. Not sure if it got loaded, the new printout from my dealer today is showing it leaving Emden on 10/17, however the next ship showing on the Volkswagen Logistics on the PWL website leaving for San Diego is on 10/24. Maybe they are getting too many cars backed up on the dock and are adding an additional ship to San Diego on 10/17?